Search the infrastructure projects that Central ministries report to MoSPI's PAIMANA project-monitoring dashboard, inspect each project's original approved cost, revised cost and cumulative expenditure, and compare the monthly reports retained since July 2025. Every figure carries the dashboard cell it came from. These are reported PAIMANA projects, not all investment in India; amounts are INR crore.

Launching opens the live playground — it may take a few seconds to wake on first use.
Put Investment Projects on your bench, then create an app from everything on it — pick a runtime, add your instructions, run it from My Apps.

Start with

Highlights

Cost overruns, measured not guessed

project_cost_revision subtracts the original approved cost from the reported revised cost. When the dashboard leaves the revised cost blank, the answer is blank too: 1,004 of the 1,853 projects in the September 2026 report carry a revised cost, and nothing is filled in for the rest.

Fifteen monthly reports, kept apart

Each report month from July 2025 to September 2026 is kept as the dashboard showed it. get_project_history shows how a project's cost and spending moved between reports. Several retrievals of the same month are captures of one report, not extra months.

Spending to date, not investment per month

Cumulative expenditure is the total spent since a project began. It is not monthly capital expenditure and it is not national investment. Every row names the publisher, the report month, the table cell and the SHA-256 of the page it came from.

Catalogue

read 2026-11-11
Entries
49
Data rows
22k
Cadence
monthly
Geography
national

Datasets

22
NameFrequencyGeographyPeriodSize
Central-sector infrastructure projects reported to PAIMANA (MoSPI IPMD)

Original approved cost, revised cost, cumulative expenditure and completion dates for each project, INR crore, as each monthly report showed them. 1,853 projects in the 2026-09 report; 22,185 project-month records over 15 report months (2025-07 to 2026-09). Reported PAIMANA projects, not all investment in India. Cumulative expenditure is spending since a project began, not monthly capex.

monthlynational2025–202622,185 rows
Aviation & Aviation Infrastructure projects (PAIMANA)

25 Aviation & Aviation Infrastructure projects in the 2026-09 report, original approved cost 21,344 crore in all; revised cost reported for 9. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Coal projects (PAIMANA)

115 Coal projects in the 2026-09 report, original approved cost 184,805 crore in all; revised cost reported for 6. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Construction projects (PAIMANA)

2 Construction projects in the 2026-09 report, original approved cost 899 crore in all; revised cost reported for 0. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Education projects (PAIMANA)

32 Education projects in the 2026-09 report, original approved cost 16,177 crore in all; revised cost reported for 12. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Electricity Generation projects (PAIMANA)

38 Electricity Generation projects in the 2026-09 report, original approved cost 378,775 crore in all; revised cost reported for 15. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Energy Storage projects (PAIMANA)

13 Energy Storage projects in the 2026-09 report, original approved cost 25,584 crore in all; revised cost reported for 13. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Healthcare projects (PAIMANA)

31 Healthcare projects in the 2026-09 report, original approved cost 20,043 crore in all; revised cost reported for 15. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Logistics Infrastructure projects (PAIMANA)

1 Logistics Infrastructure projects in the 2026-09 report, original approved cost 763 crore in all; revised cost reported for 0. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Metals & Mining projects (PAIMANA)

8 Metals & Mining projects in the 2026-09 report, original approved cost 10,103 crore in all; revised cost reported for 4. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Oil & Gas projects (PAIMANA)

102 Oil & Gas projects in the 2026-09 report, original approved cost 365,631 crore in all; revised cost reported for 102. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Railways projects (PAIMANA)

286 Railways projects in the 2026-09 report, original approved cost 593,905 crore in all; revised cost reported for 235. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Real Estate projects (PAIMANA)

15 Real Estate projects in the 2026-09 report, original approved cost 54,230 crore in all; revised cost reported for 3. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Roads & Highways projects (PAIMANA)

974 Roads & Highways projects in the 2026-09 report, original approved cost 934,082 crore in all; revised cost reported for 545. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Shipping projects (PAIMANA)

5 Shipping projects in the 2026-09 report, original approved cost 8,663 crore in all; revised cost reported for 1. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Steel projects (PAIMANA)

23 Steel projects in the 2026-09 report, original approved cost 18,781 crore in all; revised cost reported for 1. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026—
Show all 226 more
NameFrequencyGeographyPeriod
Telecommunication projects (PAIMANA)

31 Telecommunication projects in the 2026-09 report, original approved cost 158,796 crore in all; revised cost reported for 8. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026
Tourism, Hospitality & Wellness projects (PAIMANA)

1 Tourism, Hospitality & Wellness projects in the 2026-09 report, original approved cost 573 crore in all; revised cost reported for 1. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026
Transmission & Distribution projects (PAIMANA)

72 Transmission & Distribution projects in the 2026-09 report, original approved cost 241,053 crore in all; revised cost reported for 2. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026
Urban Public Transport projects (PAIMANA)

29 Urban Public Transport projects in the 2026-09 report, original approved cost 297,737 crore in all; revised cost reported for 5. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026
Waste & Water projects (PAIMANA)

23 Waste & Water projects in the 2026-09 report, original approved cost 7,790 crore in all; revised cost reported for 5. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026
Water Resources projects (PAIMANA)

27 Water Resources projects in the 2026-09 report, original approved cost 94,097 crore in all; revised cost reported for 22. Cost, revised cost, cumulative expenditure and completion dates per project, monthly from 2025-07.

monthlynational2025–2026

Ministries

17
  • Department for Promotion of Industry & Internal Trade
  • Department of Higher Education
  • Department of Sports
  • Department of Telecommunications
  • Department of Water Resources, River Development & GR
  • Ministry of Civil Aviation
  • Ministry of Coal
  • Ministry of Health & Family Welfare
  • Ministry of Housing & Urban Affairs
  • Ministry of Labour and Employment
  • Ministry of Mines
  • Ministry of Petroleum & Natural Gas
  • Ministry of Ports, Shipping and Waterways
  • Ministry of Power
  • Ministry of Railways
  • Ministry of Road Transport & Highways
  • Ministry of Steel

Capability

5

find projects

tool/find_projects

Find PAIMANA projects by native ID, project name, sector or ministry.

Query words must all appear in the combined ID/name/sector/ministry text. as_of is a timezone-qualified retrieval timestamp, not an official release date. Costs/expenditure are INR crore; blank values remain null.

get project

tool/get_project

One native project ID with original/revised cost, cumulative spending and dates.

These are reported project costs and cumulative amounts, not monthly investment flows.

get project history

tool/get_project_history

Retained project retrieval captures, newest first, with report month and cell lineage.

Only real captured versions are returned. Same-month captures must not be labelled distinct official monthly reports; older history can be absent. The latest capture of each retained report month plus four captures of the latest month are served.

project cost revision

tool/project_cost_revision

Reported revised cost minus original cost; no substitute when revised cost is blank.

project coverage

tool/project_coverage

Published report months, retrieval captures, exact scope and source freshness.

PAIMANA public dashboard is a reported project subset, not all Indian investment. Snapshot captures within one report month are not a monthly time series.

Not covered here

3

A blank revised cost stays blank

blank-revised-cost

849 of 1,853 projects in the 2026-09 report have no revised cost.

No overrun is computed for them and the original cost is never substituted.

Same-month captures are one report

captures-not-months

Several retrievals of the newest month are kept; they are captures of one report, not extra months or extra projects.

Reported projects only, not all investment

not-all-investment

Projects ministries report to MoSPI's PAIMANA dashboard.

Not national investment, not State or private projects outside it, and not a census of projects.

Known gaps

2

No reports before 2025-07

history-start

No State or district split

no-state

The dashboard table carries no State field, so projects cannot be summed by State.